# CAPM interview scorecard

Candidate: ______  Interviewer: ______  Date: ______

| # | Question | Listen for | Score 1 to 4 |
|---|---|---|---|
| 1 | A director calls three unrelated pieces of work "the transformation program." How would you describe them in a status report? | The defining test, not the label. Related components that deliver a shared benefit make a program; unrelated work grouped for funding and priority is a portfolio, or part of one. A candidate who goes by size or by the director's word is guessing. | |
| 2 | In one meeting, someone says a supplier might raise its prices, and someone else says the test server failed last night. Where does each one go? | The supplier is a risk: into the risk register with probability, impact, an owner and a planned response. The failure has happened, so it is an issue for the issue log, with an owner and a date. Neither needs a change request. | |
| 3 | The sponsor stops by your desk and asks you to add a small feature before the next review. What do you do? | Thanks the sponsor and takes the request to whoever owns scope: the product owner on an adaptive team, change control on a predictive one. Asking is not approving, however senior the person asking. | |
| 4 | Your manager asks you to show the project as green on the steering report, because the amber items will be sorted by next month. What do you do? | Reports the real status today and attaches the recovery plan that explains why it may improve. Knows this is an honesty question under PMI's Code of Ethics and Professional Conduct: you can disagree about the forecast, but you cannot misreport the present. | |
| 5 | How would you tell whether last week's project meeting worked? | Judges the meeting by its output against its purpose: decisions made, owners named, actions done by the next one. Full attendance and keeping to time are not evidence on their own. | |
| 6 | Earned value is ahead of planned value but behind actual cost. What is the project telling you? | Writes each formula with EV first. SPI is EV over PV, so above 1.0 means ahead of schedule; CPI is EV over AC, so below 1.0 means over budget. Then checks the reading against the story the project tells, not only the arithmetic. | |
| 7 | A team has renamed its four phases as sprints and calls the project agile. Is it? | Asks what a user could try at the end of each sprint. If the answer is a document or one layer of the system, the plan kept the waterfall and changed only the names. Vertical slices that each end in a working, tested increment fix it. | |
| 8 | On a Scrum team, who decides the order of the backlog, and who decides who does which task? | The product owner orders the backlog. The developers decide how to build it and who does which task. The Scrum master coaches, facilitates and gets impediments removed, and decides neither. | |
| 9 | Two department heads want the new system to follow two different versions of the same process. As the business analyst, what do you do? | Sets out the options and their consequences, finds the role that owns the decision, and puts the evidence in front of that person. The analyst facilitates the decision and records it, and does not pick a side. | |
| 10 | You need the sponsor's decision between two scope options by Thursday. How do you get it? | Interactive communication for a decision: a short meeting backed by a one-page summary, then the decision confirmed in writing. A long email is push communication and confirms nothing. | |
| 11 | Every test in the traceability matrix has passed. Is the product ready to release? | Verified, not yet validated. The owner of the requirements still has to review the result against the acceptance criteria and accept it, recorded as sign-off. The team can recommend; the owner decides. | |