What is on the PMP exam in 2026?

Bar chart of PMP domain weights, January 2021 outline against July 2026 outline: People 42% to 33%, Process 50% to 41%, Business Environment 8% to 26%. Tasks went from 35 to 26.

The PMP exam is 180 questions in 240 minutes. 170 count toward your result and 10 are unscored pretest questions placed at random. Under PMI's July 2026 outline it tests 26 tasks in three domains, People at 33%, Process at 41% and Business Environment at 26%, and about 60% of the questions use agile or hybrid approaches. PMI publishes no pass mark.

180Questions
240 minTime
26Tasks
NonePublished pass mark

Every fact below comes from PMI's own documents: the PMP Examination Content Outline for the July 2026 exam, revised 11 August 2026, the January 2021 outline it replaced, and the PMI Certification Handbook, revised June 2026.

How is the PMP exam structured?

PMI's outline says the exam has 180 questions, of which 170 are scored. The other 10 are pretest questions that "do not affect the score" and are placed at random, so answer every question as if it counts. You get 240 minutes, which is 80 seconds a question on average, our arithmetic on PMI's figures.

There are two 10-minute breaks. The first comes after the case-study section and the second about halfway through the independent questions. An optional tutorial runs before the clock starts and an optional survey after it stops, and neither uses your 240 minutes.

PMI rule

Once you review your answers and start a break, you cannot go back to the questions in the section before it. Review your answers in that section before you take each break.

PMI, PMP Examination Content Outline, July 2026

You sit the exam at a Pearson VUE test center, which PMI recommends, or online through OnVUE with a proctor. Online candidates may be asked to show their ID again after a break. In mainland China the exam is paper-based and run by ATA.

Which domains carry the most weight?

DomainWeightTasksScored questions
People33%8about 56
Process41%10about 70
Business Environment26%8about 44

The last column is our arithmetic: each weight applied to the 170 scored questions and rounded. PMI publishes percentages, not counts. Process is still the largest domain, but none of the three is small any more.

The approaches cut across all three. PMI says predictive, agile and hybrid approaches "are not isolated to any particular domain or task". About 40% of the questions represent predictive approaches and the other 60% are split between agile and hybrid. A question on resolving a conflict can just as easily be set on a Scrum team as on a construction project.

What are the 26 tasks?

PMI describes the job as 26 tasks, each with a list of enablers: the specific things a project manager does to carry the task out. These are PMI's task titles, in PMI's order.

People, 33%: 8 tasks

  • Develop a common vision
  • Manage conflicts
  • Lead the project team
  • Engage stakeholders
  • Align stakeholder expectations
  • Manage stakeholder expectations
  • Help ensure knowledge transfer
  • Plan and manage communication

Process, 41%: 10 tasks

  • Develop an integrated project management plan and plan delivery
  • Develop and manage project scope
  • Help ensure value-based delivery
  • Plan and manage resources
  • Plan and manage procurement
  • Plan and manage finance
  • Plan and optimize quality of products/deliverables
  • Plan and manage schedule
  • Evaluate project status
  • Manage project closure

Business Environment, 26%: 8 tasks

  • Define and establish project governance
  • Plan and manage project compliance
  • Manage and control changes
  • Remove impediments and manage issues
  • Plan and manage risk
  • Continuous improvement
  • Support organizational change
  • Evaluate external business environment changes

What changed from the 2021 outline?

WhatJanuary 2021 outlineJuly 2026 outline
People42%33%
Process50%41%
Business Environment8%26%
Tasks35 (14, 17 and 4)26 (8, 10 and 8)
Scored and pretest questions175 and 5170 and 10
Time230 minutes240 minutes
ApproachesAbout half predictive, half agile or hybridAbout 40% predictive, 60% agile and hybrid
New question typesNoneCase or scenario, graphic-based

The big change is Business Environment. It went from 4 tasks and 8% of the exam to 8 tasks and 26%. Governance, change control, issues and risk were Process tasks in 2021. In 2026 they sit in Business Environment, alongside compliance, continuous improvement, organizational change and changes in the external business environment.

Watch out

A course, book or question bank that says 230 minutes or 175 scored questions was written for the old exam. It treats Business Environment as 8% of the exam, when the July 2026 exam gives it 26%, more than three times as much.

One more date matters if you have not finished your training. From 1 December 2026, PMI will accept live instructor-led training toward your 35 hours only from a PMI Authorized Training Partner, a China Registered Education Provider, a GAC-accredited program or an accredited higher education institution. Self-paced on-demand courses with an end-of-course assessment are still on PMI's list. Books and practice exams alone never count, PMI says, and that includes ours.

What kinds of questions will you see?

Question typeWhat it asksWhere
Case or scenario (new)A detailed situation, sometimes with charts, then a series of questions on itAll
Graphic-based (new)Read a chart, graph, diagram or image, then answerAll
Multiple choice, single responseOne correct answerAll
Multiple responseMore than one correct answerAll
Enhanced matchingDrag items onto a chart or diagramTest center
MatchingPair items from two listsTest center
Point and clickClick the right areas of an imageTest center
Pull-down listChoose the answer from a drop-downTest center

PMI marks four types as available on every modality and four as computer-based testing only, so the online exam uses the first four. The case-study section comes first, so you start the exam reading long scenarios, and your pace in the first hour sets up the rest.

How is the PMP scored?

PMI rule

PMI publishes no pass mark. Its Certification Handbook says the passing score "is determined by sound psychometric analysis" and calls its exams criteria-based: you pass by meeting the standard of a qualified project manager, and there is no fixed percentage to aim at.

PMI Certification Handbook, revised June 2026, Establishing the Passing Score

At the end of a computer exam you get a score report: pass or fail overall, plus diagnostic information for each domain. PMI treats that result as preliminary until it confirms it, and the official report reaches the online results system no later than 10 business days after the exam. Paper-based candidates wait 6 to 8 weeks. Any figure you read online claiming a PMP pass percentage did not come from PMI. Our Pass Mark Index sets the PMP beside the other exams we cover.

What if you fail, or need to move the date?

Once PMI approves your application, or you clear an audit, you have one year to pass. Inside that year you can sit the exam up to three times, paying again for the second and third attempts. Fail three times and you wait a year from the last attempt before you reapply. If the year runs out first, you reapply with no waiting period.

Moving the exam close to the date costs money. Rescheduling or cancelling within 30 days of the appointment costs US$70 plus taxes, and within 48 hours you forfeit the fee. The exam fee itself depends on whether you are a PMI member and where you live, and member rates apply only if you joined before paying, so check your price on PMI's site first.

Who can sit the PMP?

You need 24 to 60 months of experience leading projects in the last 10 years, depending on your education, plus 35 hours of project management training or an active CAPM. Our guide to who the PMP is for covers the four paths and how PMI counts a month.

PMP study planner and exam-day checklist

PMI PMP: study planner and exam-day checklist

Domain weights and task titles come from PMI's PMP Examination Content Outline for the July 2026 exam, revised 11 August 2026. Exam rules come from that outline and the PMI Certification Handbook, revised June 2026. The 35 hours are PMI's minimum training requirement to apply; the study hours are our suggestion, split by PMI's published weights. Check PMI's PMP page before you start in case the outline has changed.

Hours by domain

DomainWeightTasks35 hours70 hours105 hours
I. People33%811.52334.75
II. Process41%1014.528.7543
III. Business Environment26%8918.2527.25
Total100%263570105

Hours are in quarter hours: 0.25 is 15 minutes, 0.5 is 30 minutes and 0.75 is 45 minutes. Domains are rounded to quarter hours so that every column adds up to its budget. PMI says about 40% of questions use predictive approaches and 60% agile or hybrid, across all three domains, so practice both in every domain.

Pace for timed practice

SetQuestionsTime at the exam's average pace
One question11 minute 20 seconds
Short timed set3040 minutes
Half the exam902 hours
Full exam1804 hours, plus two 10-minute breaks

Tasks, by domain

PMI's task titles, in PMI's order. Tick each one as you read it, study it and practice questions on it.

I. People (33%)
TaskReadStudiedPracticed
1.1 Develop a common vision[ ][ ][ ]
1.2 Manage conflicts[ ][ ][ ]
1.3 Lead the project team[ ][ ][ ]
1.4 Engage stakeholders[ ][ ][ ]
1.5 Align stakeholder expectations[ ][ ][ ]
1.6 Manage stakeholder expectations[ ][ ][ ]
1.7 Help ensure knowledge transfer[ ][ ][ ]
1.8 Plan and manage communication[ ][ ][ ]
II. Process (41%)
TaskReadStudiedPracticed
2.1 Develop an integrated project management plan and plan delivery[ ][ ][ ]
2.2 Develop and manage project scope[ ][ ][ ]
2.3 Help ensure value-based delivery[ ][ ][ ]
2.4 Plan and manage resources[ ][ ][ ]
2.5 Plan and manage procurement[ ][ ][ ]
2.6 Plan and manage finance[ ][ ][ ]
2.7 Plan and optimize quality of products/deliverables[ ][ ][ ]
2.8 Plan and manage schedule[ ][ ][ ]
2.9 Evaluate project status[ ][ ][ ]
2.10 Manage project closure[ ][ ][ ]
III. Business Environment (26%)
TaskReadStudiedPracticed
3.1 Define and establish project governance[ ][ ][ ]
3.2 Plan and manage project compliance[ ][ ][ ]
3.3 Manage and control changes[ ][ ][ ]
3.4 Remove impediments and manage issues[ ][ ][ ]
3.5 Plan and manage risk[ ][ ][ ]
3.6 Continuous improvement[ ][ ][ ]
3.7 Support organizational change[ ][ ][ ]
3.8 Evaluate external business environment changes[ ][ ][ ]

Before exam day

  • Hours booked in the calendar for your column (our suggestion)
  • At least one timed half: 90 questions in 2 hours (our suggestion)
  • Long scenarios practiced: the exam opens with a case-study section, and graphic-based questions ask you to read a chart first (PMI outline)
  • Exam booked inside your 1-year eligibility period, which starts when PMI approves your application or you clear an audit (PMI handbook)
  • Any reschedule done more than 30 days ahead: within 30 days it costs US$70 plus taxes, and within 48 hours you forfeit the fee (PMI handbook)
  • Online exam: OnVUE system test run, and ID ready to show again after each break (PMI outline)

On the day

  • Optional tutorial before the clock starts; it does not use your 240 minutes (PMI outline)
  • Review the section before each break: once a break starts you cannot go back to the questions before it (PMI outline)
  • Answer every question: the 10 pretest questions are unscored but placed at random, so you cannot tell which they are (PMI outline)

Credential Press is independent of PMI and is not affiliated with, endorsed by or authorized by PMI. PMI and PMP are marks of the Project Management Institute, Inc.

How should you prepare?

Split your hours by the weights, as the planner does, and start with Business Environment if your training was built on the 2021 outline. Practice agile and hybrid reasoning in every domain, since that is 60% of the exam. Time yourself on long scenarios as well as one-line questions, because the exam opens with them.

The PMP exam guide maps every chapter to PMI's published tasks, with predictive, agile and hybrid in every domain. For practice, the 200 PMP practice questions are sized to the domain weights, with a full rationale for every answer. A printed page can only carry single-response multiple choice, so the drag-and-drop, hotspot and pull-down formats are the one part a book cannot rehearse.

What should you do this week?

Read the eight Business Environment tasks in PMI's outline first; they are the part most material written before July 2026 underweights. If you plan live instructor-led training for your 35 hours, check your provider is on PMI's accepted list before 1 December 2026. Credential Press is independent of PMI, and nothing here comes from inside the exam.

Frequently asked questions

How many questions are on the PMP exam?

180 in 240 minutes, with two 10-minute breaks. 170 are scored and 10 are unscored pretest questions placed at random, so you cannot tell which ones they are.

What is the PMP passing score?

PMI does not publish one. Its Certification Handbook says the passing score is determined by psychometric analysis, and your score report gives pass or fail with diagnostic results for each domain.

What are the PMP domains and weights in 2026?

People 33%, Process 41% and Business Environment 26%, covering 26 tasks, under PMI's Examination Content Outline for the July 2026 exam.

What changed on the PMP exam in 2026?

Business Environment rose from 8% to 26% of the exam, the tasks went from 35 to 26, the time from 230 to 240 minutes and the pretest questions from 5 to 10. About 60% of questions now use agile or hybrid approaches, and case or scenario and graphic-based questions are new.

How many times can you take the PMP exam?

Up to three times within your one-year eligibility period, paying again for the second and third attempts. After three failures you wait one year from the last attempt before you reapply.

Do practice exams count toward the 35 training hours?

No. PMI's outline says books and practice exams alone will not be accepted as eligible commercial training.

PMP: test yourself in five minutes

Which books prepare you for the PMP exam?

Cover of PMP Exam Guide

PMP Exam Guide

A study companion for the PMI Project Management Professional (PMP) examination. 12 chapters, 370 pages.

Cover of PMP Practice Questions

PMP Practice Questions

Practice questions with full rationales, sized to the published domain weights. 218 pages.

How to credit this page

Using a figure or a passage from this page in an article, a course, a forum answer or AI-generated text? Please credit Credential Press and link to this page, so your readers can check the source and the date it was reviewed. Copy a ready-made citation:

Plain text

Markdown

HTML

Sources

Every figure above was read from PMI's own documents, except where we say the arithmetic is ours.

Credential Press is not affiliated with, endorsed by or authorized by PMI. PMI, PMP, CAPM and PMBOK are marks of the Project Management Institute, Inc.